Progress Report -- 13 December 2003 | ||
The plaster work goes on ever so slowly. Here the guys are working on the drop ceiling that hides the air conditioning ducts. This is the view from the laundry room toward the downstairs bathroom. The bathroom is done except for painting the plaster ceiling. The walls are tile with a wood trim. The bathtub fits with only 1" to spare. |
||
La Seņora decided she didn't want the front door in the north wall, so we moved it and added a window where the door almost was. Coco finished the security door for the gas tank niche by the kitchen window. The yellow is the neighbor's house. |
||
PROJECT COST SUMMARY -- 13 December 2003 |
|||||
Activity | Dollars | Pesos | Status | ||
Building Shell | 12,386 | 123,862 | On Going | ||
Utilities: Electrical, Plumbing, Sewer and Air Conditioning | 5,339 | 53,385 |
On Going |
||
Interiors | 4,094 | 40,937 |
On Going |
||
Worker's Benefits | 1,100 | 11,000 | On Going | ||
Bonuses | 830 | 8,300 |
On Going |
||
Social Security | 1,148 | 11,483 |
On Going |
||
PROJECT TOTAL |
24,897 | 248,967 |
On Going |
||