Progress Report -- 29 November 2003 | ||
One last connection to be made in the new drain system to replace the old, slightly clogged line (yellow pipe at the bottom of the picture).
The metal top for the water tank pit is finished. |
||
Maestro
and Nani are pouring the floor topping which will make the floor level
and cover the water pipes and electrical conduits that have been laid on
top of the original floor. The
original floor was built at three different times at three slightly
different levels. |
||
In the midst of the floor topping, the upstairs doors arrived. With the installation of the doors, the upstairs is now finished. These are custom made doors. The finished doors, installed, cost US$55 each. |
||
Gonzalo decided to move in now that his room is finished. I kept telling the guys that the bed frame wasn't going to fit through the tight opening at the bottom of the stairs. It didn't; so Aloyd and Coco removed one side. Then they got it upstairs. |
||
PROJECT COST SUMMARY -- 29 November 2003 |
|||||
Activity | Dollars | Pesos | Status | ||
Building Shell | 11,606 | 116,060 | On Going | ||
Utilities: Electrical, Plumbing, Sewer and Air Conditioning | 5,723 | 57,233 |
On Going |
||
Interiors | 2,148 | 21,476 |
On Going |
||
Worker's Benefits | 960 | 9,600 | On Going | ||
Bonuses |
On Going |
||||
Social Security | 953 | 9,528 |
On Going |
||
PROJECT TOTAL |
21,390 | 213,897 |
On Going |
||