Plaster,
Kitchens and Stuff |
||
The
plaster people have started. We have two crews -- two brothers and
their two sons. Each crew is doing a separate house. Each house
will take about two weeks to complete. |
||
The labor cost is $25 pesos (USD $2.50) per square meter which adds up to about USD $1,000 per house plus the cost of the plaster. The
plasterer's labor cost is based on the gross area of the walls and
ceiling; no deduction is made for the areas of windows and doors.
The rational is that the labor involved in making the neat square
returns around doors and windows is equal to or greater than the labor
of a flat wall. After watching the work, I agree. It is a
fair way to charge. |
||
This is the brick shell for the kitchen base cabinets. The top will be tile. Wooden cabinets and drawers will be inserted under the concrete tops. My original plan called for a space of 3'- 6" between the wall unit and the island, but the ladies wanted a space large enough for 3 or 4 to work for large parties, so now the spacing is 5'- 6" The stove goes in front of the window, which allows the A/C to blow the cooking heat out the window. Air conditioning work continues in the north house. The junior cleaning crew -- good enthusiasm but short attention span. They're still young enough to think it's great fun to work on their houses. |
||
|
||
|
PROJECT COST SUMMARY TO DATE |
|||
Stuff and Things -- Finishing Up |
|||
Material |
$ 110 |
||
Labor |
578 |
||
Total Stuff and Things -- 11/16 |
$688 |
||
Continuing Phases | |||
Electrical |
2,374 |
These five items are (will be) material only, Labor will be provided by the family and me. |
|
Plumbing |
510 | ||
Iron Work |
2,071 | ||
Tile |
|||
Paint |
|||
Air Conditioning |
1,220 |
These four items are (will be) material and labor. |
|
Cabinetry |
1.511 | ||
Plaster |
1,142 | ||
Stucco |
541 | ||
|
|||
Social Security payments |
4,235 | ||
|
|||
Previous Phases: |
|||
North Roof |
5,728 | ||
South Roof & Stairs |
4,964 | ||
North 2nd Floor Shell |
4,077 | ||
North 2nd Floor Slab |
4,077 | ||
South 2nd Floor Shell |
4,759 |
||
South 2nd Floor Slab |
4,514 | ||
South 1st Floor Shell |
6,934 | ||
The cost of the form lumber has not been included because it has con-siderable re-sale value. Its net cost will be included later. |
North 1st Floor Shell |
7,692 | |
Property Walls |
6,808 | ||
Property Purchase |
24,003 | ||
PROJECT TOTAL on 11/16 |
$ 87,674 |