Roof Drains
and 09 November 02 Update
 

The roof drainage work begins with pouring water on the roof to see where it wants to drain off the west side.

Then we marked the low spots where 2" drain pipes would be connected to a 4" collector pipe that would feed into a 4" down pipe

The lengths of the connecting pipes are cut to allow the 4" collector to slope down toward the main down pipe.

The finished system hanging on the side of the south building.  After the stucco and paint have been applied, maybe the drain won't be so obvious.

Roof-side view of one of the drain pipes.
 

We got the air conditioning ducts installed in the south building.  The register grilles will be installed after the plaster is applied and painted.

 

The swamp coolers will come later after the roof has been sealed.

 

Rúbin is learning to carry the concrete bucket on his head.  No hands-free yet, but no spills either.

  
 
 
Next week the plaster guys start in the south building.

PROJECT COST SUMMARY TO DATE
in US dollars converted from Mexican pesos at 9:1
 

North Roof

Material

$ 3,458

Labor

2,361

Total North Roof  -   11/09

$5,819

 
Continuing Phases

Electrical 

2,369

These five items are (will be) material only, Labor will be provided by the family and me.

Plumbing 

510

Iron Work

1,867

Tile

Paint

Social Security payments

3,599

Air Conditioning

776

Cabinetry 

1.511

Plaster

Stucco

541

 

Previous Phases:

South Roof & Stairs

4,964

North 2nd Floor Shell

4,077

North 2nd Floor Slab

4,077

South 2nd Floor Shell

4,759

South 2nd Floor Slab

4,514

South 1st Floor Shell

6,934

The cost of the form lumber has not been included because it has con-siderable re-sale value.  Its net cost will be included later.

North 1st Floor Shell

7,692

Property Walls

6,808

Property Purchase

24,003

PROJECT TOTAL on 11/09

$ 84,555