Progress Report  - 26 October 02 
 

Not much to report this week.

Coco finished the upper part of the front wall iron work.
 
The forms for the north house roof are in place, and the rebar framing is well underway.  Iniz and Jose have almost finished the stucco on the lower level of both houses.
 
But overall progress has been a bit slowed this week because of sickness and rain days thanks to Hurricane Kenna.

PROJECT COST SUMMARY TO DATE
in US dollars converted from Mexican pesos at 9:1
 

North Roof

Material

$ 1,722

Labor

820

Total North Roof  -   10/26

$2,542

 
Continuing Phases

Electrical 

2,369

These five items are (will be) material only, Labor will be provided by the family and me.

Plumbing 

510

Iron Work

1,773

Tile

Paint

Social Security payments

3,599

Air Conditioning

Cabinetry 

1.511

Plaster

Stucco

541

 

Previous Phases:

South Roof & Stairs

4,964

North 2nd Floor Shell

4,077

North 2nd Floor Slab

4,077

South 2nd Floor Shell

4,759

South 2nd Floor Slab

4,514

South 1st Floor Shell

6,934

The cost of the form lumber has not been included because it has con-siderable re-sale value.  Its net cost will be included later.

North 1st Floor Shell

7,692

Property Walls

6,808

Property Purchase

24,003

PROJECT TOTAL on 10/26

$ 80,408

Next

Return to Building Directory

Return to Main Directory