South
Roof
Slab |
||
This
week we completed the roof slab for the south building. |
||
Early in the morning just after sunrise, the guys were making few last minute adjustments before the concrete pour. |
This pour went more slowly because there were two ladders to climb and single lane traffic on the ladders. |
|
Jose begins work on the one-meter high parapet around the roof. |
Enrique completed the plumbing for the north house first floor. |
Coco completed more interior door frames and windows. |
PROJECT COST SUMMARY TO DATE |
|||
South Roof |
|||
Material |
$ 2,672 |
||
Labor |
1,994 |
||
Total South Roof - 10/05 |
$4,667 |
||
Continuing Phases | |||
Electrical |
1,894 |
These five items are (will be) material only, Labor will be provided by the family and me. |
|
Plumbing |
510 | ||
Iron Work |
1,438 | ||
Tile |
|||
Paint |
|||
Social Security payments |
3,312 | ||
Air Conditioning |
|||
Cabinetry |
755 | ||
Plaster |
|||
Stucco |
320 | ||
|
|||
Previous Phases: |
|||
North 2nd Floor Shell |
4,077 | ||
North 2nd Floor Slab |
4,077 | ||
South 2nd Floor Shell |
4,759 |
||
South 2nd Floor Slab |
4,514 | ||
South 1st Floor Shell |
6,934 | ||
The cost of the form lumber has not been included because it has con-siderable re-sale value. Its net cost will be included later. |
North 1st Floor Shell |
7,692 | |
Property Walls |
6,808 | ||
Property Purchase |
24,003 | ||
PROJECT TOTAL on 10/05 |
$ 75,495 |