Progress
Report -12 October 02 |
||
Coco is giving the front iron work a primer coat of battle ship gray. Later it will get a final coat of white. |
||
Like a monkey, Rúbin scampers around on that little ledge 20 feet above the ground helping Jose attach the rebar frames for the parapet. The parapet is now finished on three sides. The west side will take a while longer because that is the side where the roof drains. Next week we will begin work on the drainage system and the west parapet. It's hard to see in the pictures, but there is a gentle slope to the west. We'll also compete the stairs to the roof next week. All the rebar is in place; we need only eight more step forms. |
||
PROJECT COST SUMMARY TO DATE |
|||
South Roof and Stairs |
|||
Material |
$ 1,814 |
||
Labor |
2,661 |
||
Total South Roof - 10/12 |
$4,475 |
||
Continuing Phases | |||
Electrical |
2,245 |
These five items are (will be) material only, Labor will be provided by the family and me. |
|
Plumbing |
510 | ||
Iron Work |
1,506 | ||
Tile |
|||
Paint |
|||
Social Security payments |
3,312 | ||
Air Conditioning |
|||
Cabinetry |
1.511 | ||
Plaster |
|||
Stucco |
320 | ||
|
|||
Previous Phases: |
|||
North 2nd Floor Shell |
4,077 | ||
North 2nd Floor Slab |
4,077 | ||
South 2nd Floor Shell |
4,759 |
||
South 2nd Floor Slab |
4,514 | ||
South 1st Floor Shell |
6,934 | ||
The cost of the form lumber has not been included because it has con-siderable re-sale value. Its net cost will be included later. |
North 1st Floor Shell |
7,692 | |
Property Walls |
6,808 | ||
Property Purchase |
24,003 | ||
PROJECT TOTAL on 10/12 |
$ 77,727 |