Progress Report - 24 Aug 02

Inspector dog Jason surveys the job. And checks on the rebar and electrical work.      Concrete soon.      

 

PROJECT COST SUMMARY TO DATE
in US dollars converted from Mexican pesos at 9:1
 

 North 2nd Floor Slab

Material

$ 1,635

Labor

1,183

Total N 2nd Floor Slab - 8/24

$ 2,819

 
Continuing Phases

Electrical 

1,172

These five items are (will be) material only, Labor will be provided by the family and me.

Plumbing 

454

Iron Work

411

Tile

Paint

Social Security payments

2,669

Air Conditioning

Cabinetry 

Plaster

Stucco

 

Previous Phases:

South 2nd Floor Shell

4,759

South 2nd Floor Slab

4,514

South 1st Floor Shell

6,934

The cost of the form lumber has not been included because it has con-siderable re-sale value.  Its net cost will be included later.

North 1st Floor Shell

7,692

Property Walls

6,808

Property Purchase

24,003

PROJECT TOTAL on 8/24

$ 62,234