Progress Report - 24 Aug 02 |
||
Inspector dog Jason surveys the job. And checks on the rebar and electrical work. Concrete soon. |
||
PROJECT COST SUMMARY TO DATE |
|||
North 2nd Floor Slab |
|||
Material |
$ 1,635 |
||
Labor |
1,183 |
||
Total N 2nd Floor Slab - 8/24 |
$ 2,819 |
||
Continuing Phases | |||
Electrical |
1,172 |
These five items are (will be) material only, Labor will be provided by the family and me. |
|
Plumbing |
454 | ||
Iron Work |
411 | ||
Tile |
|||
Paint |
|||
Social Security payments |
2,669 | ||
Air Conditioning |
|||
Cabinetry |
|||
Plaster |
|||
Stucco |
|||
|
|||
Previous Phases: |
|||
South 2nd Floor Shell |
4,759 |
||
South 2nd Floor Slab |
4,514 | ||
South 1st Floor Shell |
6,934 | ||
The cost of the form lumber has not been included because it has con-siderable re-sale value. Its net cost will be included later. |
North 1st Floor Shell |
7,692 | |
Property Walls |
6,808 | ||
Property Purchase |
24,003 | ||
PROJECT TOTAL on 8/24 |
$ 62,234 |