Progress Report - 31 Aug 02 |
||
The electrical rough-in is complete in the two south units. |
||
The boxes and conduits have been recessed into the brick walls -- although it is a bit hard to see in these pictures. When the wall is plastered, all this will be covered. These pictures are from the first floor south where the concrete floor slab has not yet been poured on the dirt 'sub-floor.' Perhaps next week. |
||
The
concrete guys returned to perform their amazing bucket on the head
balancing act. More guys this time, so the total time was just
four hours. |
||
PROJECT COST SUMMARY TO DATE |
|||
North 2nd Floor Shell |
|||
Material |
$ 1,111 |
||
Labor |
0 |
||
Total N 2nd Floor Shell - 8/31 |
$1,111 |
||
Continuing Phases | |||
Electrical |
1,302 |
These five items are (will be) material only, Labor will be provided by the family and me. |
|
Plumbing |
510 | ||
Iron Work |
735 | ||
Tile |
|||
Paint |
|||
Social Security payments |
2,669 | ||
Air Conditioning |
|||
Cabinetry |
|||
Plaster |
|||
Stucco |
|||
|
|||
Previous Phases: |
|||
North 2nd Floor Slab |
4,077 | ||
South 2nd Floor Shell |
4,759 |
||
South 2nd Floor Slab |
4,514 | ||
South 1st Floor Shell |
6,934 | ||
The cost of the form lumber has not been included because it has con-siderable re-sale value. Its net cost will be included later. |
North 1st Floor Shell |
7,692 | |
Property Walls |
6,808 | ||
Property Purchase |
24,003 | ||
PROJECT TOTAL on 8/24 |
$ 65,114 |