Progress Report - 17 Aug 02
 

The shell of the second floor south is finished.  The floor slab forms have been removed and reinstalled in the north building in preparation for pouring the second floor on that side.

Another mason has been added to the team to speed up the work.

Coco has begun the iron work for the front wall.  Pictures of that soon.

 

PROJECT COST SUMMARY TO DATE
in US dollars converted from Mexican pesos at 9:1
 

 North 2nd Floor Slab

Material

$ 198

Labor

456

Total N 2nd Floor Slab - 8/17

$ 653

 
Continuing Phases

Electrical 

1,072

These five items are (will be) material only, Labor will be provided by the family and me.

Plumbing 

363

Iron Work

411

Tile

Paint

Social Security payments

2,369

Air Conditioning

Cabinetry 

Plaster

Stucco

 

Previous Phases:

South 2nd Floor Shell

4,759

South 2nd Floor Slab

4,514

South 1st Floor Shell

6,934

The cost of the form lumber has not been included because it has con-siderable re-sale value.  Its net cost will be included later.

North 1st Floor Shell

7,692

Property Walls

6,808

Property Purchase

24,003

PROJECT TOTAL on 8/17

$ 59,578