Progress
Report - 17 Aug 02 |
||
The shell of the second floor south is finished. The floor slab forms have been removed and reinstalled in the north building in preparation for pouring the second floor on that side. Another mason has been added to the team to speed up the work. Coco has begun the iron work for the front wall. Pictures of that soon. |
||
PROJECT COST SUMMARY TO DATE |
|||
North 2nd Floor Slab |
|||
Material |
$ 198 |
||
Labor |
456 |
||
Total N 2nd Floor Slab - 8/17 |
$ 653 |
||
Continuing Phases | |||
Electrical |
1,072 |
These five items are (will be) material only, Labor will be provided by the family and me. |
|
Plumbing |
363 | ||
Iron Work |
411 | ||
Tile |
|||
Paint |
|||
Social Security payments |
2,369 | ||
Air Conditioning |
|||
Cabinetry |
|||
Plaster |
|||
Stucco |
|||
|
|||
Previous Phases: |
|||
South 2nd Floor Shell |
4,759 |
||
South 2nd Floor Slab |
4,514 | ||
South 1st Floor Shell |
6,934 | ||
The cost of the form lumber has not been included because it has con-siderable re-sale value. Its net cost will be included later. |
North 1st Floor Shell |
7,692 | |
Property Walls |
6,808 | ||
Property Purchase |
24,003 | ||
PROJECT TOTAL on 8/17 |
$ 59,578 |