PROJECT COST SUMMARY - 10 May 2003 | |||||
Activity | Dollars | Pesos | Status | ||
Land and Property Walls |
$27,484 |
$274,842 |
Completed |
||
Building Shell and Patio |
60,365 |
603,651 |
Completed |
||
Utilities:
Electrical, Plumbing, Sewer and Air Conditioning |
10,574 |
105,739 |
On Going |
||
Interiors |
21,011 |
210,114 |
On Going |
||
Social Security |
5,868 |
58,678 |
On Going |
||
PROJECT TOTAL |
$ 125,302 |
$1,253,024 |
On Going |
||
Cost per unit | $ 31,326 | $ 313,256 | On Going |