Construction
Workers Day Update for 3 May 2003 |
||
Today, May 3, is Construction Workers Day. In celebration of the day, a brightly decorated cross was placed atop the building. On the left is a picture on 3 May 2002. On the right is one on 3 May 2003. |
||
And the patio then and now. If the cabinet makers will hurry up, there won't be a picture on 3 May 2004 -- I hope. We now have cabinets in 2 of 4 bathrooms and 2 of 4 kitchens and bedroom closets for 2 houses, but we have interior doors in only one house. |
||
Jesus completed another bathroom cabinet set. Ruben is carrying in the pieces for Jesus to assemble in the bathroom.
Manuel is installing a ceiling fan in Paco's bedroom. We should have all 23 fans installed before the end of next week. |
||
For
last
year's party we cooked carne asada and sausages, this year the ladies made pork
in chile colorado sauce, rice, beans and tortillas. Very
good. They made a lot, so we took some to several of our
neighbors. |
||
PROJECT COST SUMMARY - 3 May 2003 | |||||
Activity | Dollars | Pesos | Status | ||
Land and Property Walls |
$27,484 |
$274,842 |
Completed |
||
Building Shell and Patio |
60,195 |
601,945 |
Completed |
||
Utilities:
Electrical, Plumbing, Sewer and Air Conditioning |
9,955 |
99,550 |
On Going |
||
Interiors |
20,569 |
205,692 |
On Going |
||
Social Security |
5,868 |
58,678 |
On Going |
||
PROJECT TOTAL |
$ 124,071 |
$1,240,707 |
On Going |