One
Year on the Job |
||
This
week we passed the first anniversary of the start of the project. |
||
On
the left, the view from the SW. |
||
This
picture comes the closest to showing the colors correctly. |
PROJECT COST SUMMARY TO DATE |
||||
Stuff and Things -- |
Dollars at 10:1 | Pesos | ||
Material |
$ 1,508 |
$ 15,084 |
||
Labor |
3,046 |
30,455 |
||
Total Stuff and Things |
4,554 |
45,539 |
||
Continuing Phases | ||||
These 5 items are (will be) material only. Labor will be provided by the family and me. |
Electrical |
3,156 |
31,564 |
|
Plumbing |
1,958 |
19,575 |
||
Iron Work |
2,381 |
23,813 |
||
Tile |
4,615 |
46,151 |
||
Paint, inside |
||||
These 7 items are (will be) material and labor. |
Air Conditioning |
3,130 |
31,302 |
|
Cabinetry |
3,380 |
33,802 |
||
Plaster |
5,642 |
56,419 |
||
Stucco |
5,208 |
52,075 |
||
Window Glass |
||||
Roof Sealing |
948 | 9,476 | ||
Paint, outside |
1,838 | 18,383 | ||
|
||||
Social Security payments |
4,685 |
46,849 |
||
|
||||
Previous Phases: |
||||
North Roof |
5,238 |
52,375 |
||
South Roof & Stairs |
4,467 |
44,674 |
||
North 2nd Floor Shell |
3,431 |
34,310 |
||
North 2nd Floor Slab |
3,669 |
36,692 |
||
South 2nd Floor Shell |
4,282 |
42,828 |
||
The cost of the form lumber has not been included because it has considerable re-sale value. Its net cost will be included later. |
South 2nd Floor Slab |
4,063 |
40,630 |
|
South 1st Floor Shell |
6,241 |
62,406 |
||
North 1st Floor Shell |
6,923 |
69,228 |
||
Property Walls |
5,882 |
58,815 |
||
Property Purchase |
21,621 |
216,208 |
||
PROJECT TOTAL 02/08/03 |
$ 107,194 |
$ 1,071,936 |