The South Building Second Floor Slab
Part 2 - Rebar and Plumbing Rough-in 

Almost all the form work is done, so the rebar work begins.

The slab for the living room needs a stiffening beam across the center of the room; but a beam at that location would interfere with the layout of the windows because the beam must rest on columns.  We elected to have two beams, each at a third point of the room so the columns would fall between the windows.  

The beams will hang down about 6" below the ceiling of the living room below.  The beams require a massive frame made up of eight lengths of 1/2" rebar.

Here one rebar frame is already in place as the the other is being lifted up and placed into its slot.

The drain pipes for the bathroom and kitchen are in place.  After the concrete has cured, the pipes will be cut off to the proper length.  

The water pipes and electrical will be roughed-in after the rebar work is completed next week (I hope).  

This phase seems to go so slowly. It is becoming apparent that we will not meet our goal of occupancy by Christmas.

 




The material costs shown here do not reflect the true costs for this phase because we have bought several things (electrical, plumbing, etc) for the entire project.

Cost to date of the south building
2nd floor slab, stairs and rough-ins
(US$   at 9 pesos per dollar)




The cost of the form lumber has not been included because it has considerable re-sale value.  Its net cost will be included later.

Material   

  $ 1,235

Labor

  2,025

S 2nd floor slab on 7/06

 3,260

Previous Phases:

   South 1st Floor Shell

7,648

   North 1st Floor Shell

7,958

   Property Walls

7,085

   Property Purchase

24,003

PROJECT TOTAL on 7/06

$ 49,953