Beat Goes On Update for 31 May 2003 |
||
The ladies have finally resigned themselves to a longer wait for their move-in. Which is not to say they have let up the pressure on us to hurry up. Iniz and Nanny continue to set tile in the bathrooms. |
||
Enrique
is installing the main water cutoff valves at the front wall. Next
week the pipes will be extended under the sidewalk to the street for
connection to the water main by a city crew. Ruben is running wiring to the roof for the water pumps and the air conditioners. |
||
Manolo
has almost finished the brick work in the back utility walkway. |
||
PROJECT COST SUMMARY - 31 May 2003 | |||||
Activity | Dollars | Pesos | Status | ||
Land and Property Walls |
$27,484 |
$274,842 |
Completed |
||
Building Shell and Patio |
60,926 |
609,263 |
Completed |
||
Utilities:
Electrical, Plumbing, Sewer and Air Conditioning |
11,959 |
119,586 |
On Going |
||
Interiors |
22,226 |
222,258 |
On Going |
||
Social Security |
6,433 |
64,332 |
On Going |
||
PROJECT TOTAL |
$ 129,025 |
$1,290,254 |
On Going |
||
Cost per unit | $ 32,256 | $ 322,563 | On Going |