Tile 22 March 03 Update |
||
We are well underway with the floor tile in the north building. We have painted the wall in the family room and hallway from the chair rail up. The lower wall will be painted after the grout has been set. The grouting work always splatters on the lower wall, so painting later. The chair rails will be ceramic tile border strips that will be applied after the painting is finished. The pink room for the girls and blue for the boys. These rooms will not have two-color walls and chair rails. The picture of the tile in the boy's room is closest to the true color. |
||
PROJECT COST SUMMARY TO DATE |
||||
Stuff and Things -- |
Dollars at 10:1 | Pesos | ||
Material |
$ 1,438 |
$ 14,376 |
||
Labor |
3,246 |
32,455 |
||
Total Stuff and Things |
4,683 |
46,831 |
||
Continuing Phases | ||||
These 3 items are (will be) material only. Labor will be provided by the family and me. |
Electrical |
3,398 |
33,984 |
|
Plumbing |
2,402 |
24,021 |
||
Iron Work |
2,527 |
25,272 |
||
Cabinetry |
4,210 |
42,095 |
||
Window Glass |
900 |
9,000 |
||
Paint, inside |
717 | 7,166 | ||
Tile |
5,701 |
57,005 |
||
Patio Brick Work |
1,345 | 13,450 | ||
|
||||
Social Security payments |
5,642 |
56,419 |
||
Form Lumber |
1,975 |
19,754 |
||
Previous Phases: |
||||
Air Conditioning |
3,130 |
31,302 |
||
Plaster |
5,642 |
56,419 |
||
Stucco |
5,328 |
53,275 |
||
Paint, outside |
2,867 | 28,866 | ||
Roof Sealing |
948 | 9,476 | ||
North Roof |
5,238 |
52,375 |
||
South Roof & Stairs |
4,467 |
44,674 |
||
North 2nd Floor Shell |
3,431 |
34,310 |
||
North 2nd Floor Slab |
3,669 |
36,692 |
||
South 2nd Floor Shell |
4,282 |
42,828 |
||
|
South 2nd Floor Slab |
4,063 |
40,630 |
|
South 1st Floor Shell |
6,241 |
62,406 |
||
North 1st Floor Shell |
6,923 |
69,228 |
||
Property Walls |
5,882 |
58,815 |
||
Property Purchase |
21,621 |
216,208 |
||
PROJECT TOTAL 03/22/03 |
$ 117,090 |
$ 1,170,903 |