Kitchen
Cabinets |
||
The kitchen cabinets are installed in Martha's house. The cabinets for Coco's house should be ready next week. The two upstairs apartments will get cabinets in several more weeks. Interior painting and tile work will begin next week. |
||
Enrique has finished painting the door and window frames in three of the four apartments. The exterior painting is done except for some trim and touch-ups. Now we are beginning to prep the patio for the brick pavers.
|
||
PROJECT COST SUMMARY TO DATE |
||||
Stuff and Things -- |
Dollars at 10:1 | Pesos | ||
Material |
$ 1,508 |
$ 15,084 |
||
Labor |
3,046 |
30,455 |
||
Total Stuff and Things |
4,554 |
45,539 |
||
Continuing Phases | ||||
These 4 items are (will be) material only. Labor will be provided by the family and me. |
Electrical |
3,156 |
31,564 |
|
Plumbing |
1,958 |
19,575 |
||
Iron Work |
2,451 |
24.512 |
||
Paint, inside |
||||
These 7 items are material and labor. |
Air Conditioning |
3,130 |
31,302 |
|
Cabinetry |
3,380 |
33,802 |
||
Plaster |
5,642 |
56,419 |
||
Stucco |
5,328 |
53,275 |
||
Window Glass |
600 |
6000 |
||
Roof Sealing |
948 | 9,476 | ||
Paint, outside |
2,867 | 28,866 | ||
Tile |
4,615 |
46,151 |
||
|
||||
Social Security payments |
5,007 |
50,068 |
||
Form Lumber |
1,975 |
19,754 |
||
Previous Phases: |
||||
North Roof |
5,238 |
52,375 |
||
South Roof & Stairs |
4,467 |
44,674 |
||
North 2nd Floor Shell |
3,431 |
34,310 |
||
North 2nd Floor Slab |
3,669 |
36,692 |
||
South 2nd Floor Shell |
4,282 |
42,828 |
||
|
South 2nd Floor Slab |
4,063 |
40,630 |
|
South 1st Floor Shell |
6,241 |
62,406 |
||
North 1st Floor Shell |
6,923 |
69,228 |
||
Property Walls |
5,882 |
58,815 |
||
Property Purchase |
21,621 |
216,208 |
||
PROJECT TOTAL 02/22/03 |
$ 111,329 |
$ 1,113,291 |