Progress Report - 25 January 2003
I haven't made any posts for the past couple of weeks because the only action has been doing the plaster and stucco.  Now the plaster is done, and the stucco is finished except for the trim around the curved windows.

The plaster man is making the trim around the curved windows on the second floor.  The trim will be painted white against a yellow wall.

The trim on the first floor windows will come after the scaffolding is removed.

Rubin is spraying on a prime/sealer coat to seal the stucco and prepare it to receive the finish paint which will began next week.

     