| Progress
Report -- 27
December 2003 Almost Finished |
||
![]() |
The
construction is finished. We'll probably need one more week to
complete the finish work inside the house, then a few days to build new
sidewalks. |
![]() |
![]() |
Ruben and I are well underway hanging ceiling fans and installing switch and receptacle plates. |
![]() |
![]() |
Coco completed the painting of the window frames and security bars. The glass guys will come on Monday. |
![]() |
|
PROJECT COST SUMMARY -- 27 December 2003 |
|||||
| Activity | Dollars | Pesos | Status | ||
| Building Shell | 12,788 | 127,879 | Done | ||
| Utilities: Electrical, Plumbing, Sewer and Air Conditioning | 5,388 | 53,879 |
On Going |
||
| Interiors | 5,465 | 54,650 |
On Going |
||
| Worker's Benefits | 1,210 | 12,100 | On Going | ||
| Bonuses | 830 | 8,300 |
On Going |
||
| Social Security | 1,148 | 11,483 |
On Going |
||
|
PROJECT TOTAL |
26,861 | 268,611 |
On Going |
||