        Floor Tile and Electrical 5 April 2003 Update | ||
|  | Enrique
        is preparing the electrical backboard for the north building by
        attaching the breaker panels, telephone junction blocks, and TV antenna
        splitters.  Each room is on a separate breaker.  The bedrooms
        and the family room have telephone and TV jacks. |  | 
|  | Santa
        Claus in his summer uniform is attaching "F" connectors to TV
        cables. Iniz is laying tile in Andrea's condo. He has already completed the floor tile for Martha and Rosa. |  | 
|  | Rubin's job is to cut and fit the odd size edge pieces. |  | 
|  | Nanny is rubbing grout into the spaces between the tiles. 
 
 After the grout has set for awhile, Manolo and Nanny wash the tiles to remove the excess grout before it becomes hard set. |  | 
| Beginning this week, the usual detailed cost report now has its own page which can be found on the Page Directory at the end of the House Building list. | ||
| PROJECT COST SUMMARY - 5 April 2003 | |||||
| Activity | Dollars | Pesos | Status | ||
| Land and Property Walls | $27,484 | $274,842 | Completed | ||
| Building Shell and Patio | 59,102 | 591,023 | Completed | ||
| Utilities: 
          Electrical, Plumbing, Sewer and Air Conditioning | 9,008 | 90,082 | On Going | ||
| Interiors | 17,868 | 178,681 | On Going | ||
| Social Security | 5,600 | 55,998 | On Going | ||
| PROJECT TOTAL | $119,270 | $1,192,705 | On Going | ||